- October 21, 2024 Onboarding starts
- Information gathering
- Access to Alma Sandbox
- November 8, 2024 Test Load sent to Ex Libris
- Data migration and mapping forms to Ex Libris
- January 10 - February 9, 2025 Implementation kickoff
- Intro To Alma Core Concepts
- Fulfillment Core Concepts and Workflow Questions
- User Management Core Concepts
- February 9 - March 7, 2025 Test Load begins
- Cataloging Core Concepts and Workflow Questions
- Acquisitions Core Concepts and Workflow Questions
- Configuration Form
- March 7 - July 3, 2025 Data and Configuration Validation
- Delivery of test load data in Alma
- Validation of migrated data, documentation of changes to migration decisions
- Check and adjust workflows
- 3rd party integrations configured, tested and validated
- Scheduled LASR downtime to configure and test integration
- Local documentation of workflows, staff training
- Weekly "Office hours" as we approach go-live
- Technical services and acquisitions freeze - late June 2025
- Affects Acquisitions and Cataloging in Sierra
- Cutover start – July 6, 2025
- Fulfillment cutover start – July 21, 2025
- Cease circulation functions in Sierra - Offline Circ
- Go live – July 23, 2025
- Continued regular contact with Ex Libris Project Team for 4-6 weeks
The full, week-by-week, schedule can be found here.