Alma Implementation

General Timeline/Overview

  • October 21, 2024 Onboarding starts
    • Information gathering
    • Access to Alma Sandbox 
  • November 8, 2024 Test Load sent to Ex Libris
    • Data migration and mapping forms to Ex Libris
  • January 10 - February 9, 2025 Implementation kickoff
    • Intro To Alma Core Concepts
    • Fulfillment Core Concepts and Workflow Questions
    • User Management Core Concepts
  • February 9 - March 7, 2025 Test Load begins
    • Cataloging Core Concepts and Workflow Questions
    • Acquisitions Core Concepts and Workflow Questions
    • Configuration Form
  • March 7 - July 3, 2025 Data and Configuration Validation
    • Delivery of test load data in Alma
    • Validation of migrated data, documentation of changes to migration decisions
    • Check and adjust workflows
    • 3rd party integrations configured, tested and validated
      • Scheduled LASR downtime to configure and test integration 
    • Local documentation of workflows, staff training
      • Weekly "Office hours" as we approach go-live
  • Technical services and acquisitions freeze - late June 2025
    • Affects Acquisitions and Cataloging in Sierra
  • Cutover start – July 6, 2025
  • Fulfillment cutover start – July 21, 2025
    • Cease circulation functions in Sierra - Offline Circ 
  • Go live – July 23, 2025
    • Continued regular contact with Ex Libris Project Team for 4-6 weeks

The full, week-by-week, schedule can be found here.